Construction UpdateRG Pleiaddes, Sector 1
Last updated: October 2026
RG Pleiaddes launched in September 2025 and is currently under construction, with completion targeted around September 2029. This page is updated on a monthly cycle, so anyone tracking a construction-linked payment plan is working from the current picture rather than launch-day renders.
Current Stage of Work: October 2026
As of October 2026, construction is active on the Sector 1 site using the aluminium formwork (Mivan) system, with work moving tower by tower from the foundations laid in early 2026.
We record the slab reached on each tower every month rather than a general statement. If you want this month's dated photo set for a specific tower, ask and we'll send it.
October 2026 photo set
Dated photographs from this month's site visit, tower by tower, with a visible date caption on each frame. Ask and we'll send the full set on WhatsApp.
Approved elevation, six towersArtistic impression
Aluminium formwork
Built on Mivan Shuttering, Not Just Renders
RG Pleiaddes is built using aluminium formwork, commonly called Mivan, rather than conventional brick-and-block construction. In practical terms, walls and slabs are cast together as a single monolithic RCC pour, which cuts down on the joints and seams where seepage typically starts, tightens dimensional tolerances between one flat and the next, shortens the casting cycle per floor, and gives the finished structure better resistance to seismic movement.
It's a slower story to tell in a brochure than a lobby render, but it's the part of the build that actually determines how the flat holds up ten years in.
- SystemAluminium formwork (Mivan)
- StructureMonolithic RCC
- Joints & seamsSubstantially fewer
- Casting cycleFaster per floor
- Seismic performanceImproved over brick-and-block
Sept 2025 → Sept 2029
Milestone Timeline
- Sept 2025Launch and UP RERA registration
- Early 2026Excavation, foundation, early tower structure
- NextSuperstructure, podium to mid-rise, tower by tower
- ThenSuperstructure completion and external finishing
- ThenMEP fit-out and internal finishing
- ThenClubhouse and landscaping
- ≈ Sept 2029Occupancy certificate and possession
Intermediate dates are governed by the registered RERA timeline and the developer's progress circulars, and are confirmed stage by stage rather than by calendar.
Tentative layout
Where Each Tower Sits
Six towers around a central green spine, with the clubhouse block and podium pool to the east. Tower heights on the tentative plan run from S+24 to S+29. Tap to enlarge.
Tentative site planSubject to approval
Monthly cycle
How We Keep This Page Current
This page is updated on a monthly cycle directly from site-visit photographs and the developer's progress circulars. Photographs are illustrative of the stage of construction at the time they were taken; final specifications, elevations, and finishes are governed by the Agreement for Sale, not by any image on this page.
See It for Yourself
Numbers and photos only go so far. If you're seriously evaluating RG Pleiaddes, book a site visit and walk the tower in person. We'll arrange access and answer questions on the spot.
What is the current construction stage of RG Pleiaddes?
RG Pleiaddes is under active construction following its September 2025 launch. This page is updated monthly, and the dated photo set for the current month is sent on request.
When is RG Pleiaddes expected to be ready for possession?
Possession is targeted around September 2029, as per the timeline registered with UP RERA under UPRERAPRJ415309/09/2025.
How does a construction-linked payment plan work here?
Each instalment is tied to a completed stage of work rather than a fixed calendar date, so payments track the slab actually cast. We can walk you through the current schedule against the stage on site.